South Tyneside Regeneration & Investment Briefing

Funding, places and delivery.

Cover of the Q3 2026 edition
Contents of this edition

Funding, places and delivery. A briefing for the organisations bringing forward homes and regeneration across South Shields, Hebburn, Jarrow, Boldon and the wider borough.

The Word, South ShieldsIllustrative visualisation, AI-generated; adapted from a photograph by John Lord, CC BY 2.0

Dates and decisions to watch

As at 19 September 2026 Published position
South Tyneside Local Plan Adopted 30 July 2026; sets a housing requirement of at least 5,253 homes 2023–2040. [17]
Biddick Hall Pride in Place (phase 2) Neighbourhood Board formed; first meeting expected September 2026; ten-year Regeneration Plan and four-year Investment Plan due to MHCLG 30 November 2026. [6,11]
Jarrow Forward Pride in Place (phase 1) Ten-year Regeneration Plan 2026–2036 submitted to Government October 2025 and approved April 2026; delivery of the first projects under way; no plan deadline applies (phase 1). [7,9,10,33]
Pride in Place Impact Fund £750,000 in each of 2025/26 and 2026/27; national guidance requires commitment by 31 March 2027; local South Tyneside distribution not yet published. [13,14]
Miller Homes, Westoe (former South Tyneside College site) 198 homes; final Government planning approval confirmed 25 March 2026. [27]

Figures in this briefing cover different programmes, geographies and periods. They should not be added into a single borough investment total.

The funding landscape

Up to £46 billion over ten years

Homes England and its subsidiary, the National Housing Bank, have up to £46 billion to deploy across England to 2036. [1]

The joint Investment Prospectus, published 31 March 2026 ahead of the National Housing Bank's opening on 1 April, brings grant, land and finance into one framework. [1]

Stream Amount What it funds / who it reaches
Social and Affordable Homes Programme 2026–2036 At least £27bn outside London; £39bn nationally Capital grant for social/affordable rent, shared ownership, supported housing, estate regeneration.
Housing and Infrastructure Capital Grant About £3.1bn (Homes England's share of the £5bn national pot) Land assembly, remediation, strategic infrastructure.
National Housing Delivery Fund Up to £16bn Loans, equity, guarantees, including funding devolved to mayoral strategic authorities such as NECA.

Programme milestones

Date Milestone
31 March / 1 April 2026 Investment Prospectus published / National Housing Bank opens [1]
1 April 2026 North East's integrated settlement begins its first year (2026/27) [see regions/north-east.md, source 4]
25 August 2026 First wave: 33 strategic partners confirmed outside London, summing to £9,584.1m and 73,617 homes; Newcastle City Council named for the North East (966 homes, £141.4m); Karbon Homes Limited (2,533 homes, £350.0m nationally) is also a first-wave partner and is separately active on named South Tyneside schemes [2]
24 August 2026 MHCLG's companion release gives the North East a regional estimate of £445m / c.3,400 homes of first-wave Strategic Partnership spend — a regional figure, not a South Tyneside award [3]
30 July 2026 South Tyneside Local Plan adopted [17]
30 November 2026 Biddick Hall Pride in Place ten-year plan due to MHCLG (phase 2) [11]

Grant, land and finance (products and routes)

Family Product Purpose Typical user
Grant Social and Affordable Homes Programme Affordable tenures, supported housing, estate regeneration RPs, councils, developer partners
Grant Housing and Infrastructure Capital Grant Viability gaps, infrastructure, land assembly, remediation Councils, landowners, master developers
Land Homes England land Acquisition, enabling, disposal Developers of all sizes
Finance SME Accelerator Loan Site finance for smaller builders SME housebuilders
Finance Senior/mezzanine debt Project funding for brownfield and later-living schemes Developers and funds
Finance Infrastructure loans Long-term (up to 15 years) upfront infrastructure finance Developers and councils
Finance Low-interest RP loans Unlocking capital investment in social/affordable homes Registered Providers
Finance Guarantees Bonds and loans reducing institutional financing costs Funds and RPs

Housing and infrastructure grant for South Tyneside is more likely to route through NECA's own Brownfield Housing Fund and its integrated settlement; SAHP grant remains administered by Homes England and is not devolved to NECA. [1, see regions/north-east.md]

Regional routes: North East

Regional routes: see regions/north-east.md for NECA's status as an established mayoral strategic authority, the Mayor's Brownfield Housing Fund, the Plan for Homes / National Housing Delivery Fund allocation, the SAHP first-wave regional figures, Mayoral Development Zones, the North East Investment Zone and the regional skills offer.

No Mayoral Development Zone or Investment Zone site is named for South Tyneside; the announced MDZs cover Newcastle/Gateshead, Durham City and Sunderland, and the Investment Zone's four sites are Blyth, Sunderland/South Tyneside (International Advanced Manufacturing Park boundary), the Tyne economic corridor and NETPark. The Tyne economic corridor Investment Zone site and the IAMP boundary both touch South Tyneside, but this is jobs/business-space money, not housing grant. [see regions/north-east.md]

Scheme requirement Route to establish (South Tyneside) What to resolve
Social and affordable homes Homes England's SAHP 2026–2036, by continuous market engagement or strategic partnership, read against NECA's published 60% Social Rent priority and its six spatial priorities. No South Tyneside-specific SAHP allocation is published; the sole named North East partner is Newcastle City Council (966 homes, £141.4m). MHCLG's 24 August 2026 release gives the North East a regional estimate of £445m / c.3,400 homes — a regional figure, not a South Tyneside award. Karbon Homes Limited, a first-wave national partner (2,533 homes, £350.0m), is separately active in South Tyneside on named extra-care and supported-living schemes, but neither is evidence of a South Tyneside SAHP allocation. [2,3,25,26] Tenure mix, delivery partner, grant requirement, timing.
Land, infrastructure, abnormal costs South Tyneside Council, then NECA's Brownfield Housing Fund / integrated settlement housing and land budget. No named South Tyneside Brownfield Housing Fund award was found in the sources checked for this brief — open. [see regions/north-east.md] Why the site is stalled, what intervention unlocks it, the council's support for the NECA business case.
Additional affordable-housing support NECA housing and land team, alongside the Plan for Homes pipeline. SAHP secured or progressing; the remaining gap and deliverability.
Debt, equity or guarantees National Housing Bank via Homes England. Borrower/investment structure, security, route to repayment. [1]

Who decides what (decisions and public contacts)

  1. Homes England / National Housing Bank — Final SAHP funding and contractual decisions; the Bank assesses its finance investments. [1,18]
  2. North East Mayoral Strategic Authority (NECA) — Regional priorities, tenure mix, SAHP strategic priorities; Brownfield Housing Fund; integrated settlement; Plan for Homes. [see regions/north-east.md]
  3. South Tyneside Council — Local housing need, planning authority (Local Plan adopted 30 July 2026), council land, its own housing programme via South Tyneside Homes; accountable body for the Jarrow and Biddick Hall Pride in Place neighbourhoods. [17,6,7]
  4. Two Pride in Place neighbourhood boards — Jarrow Forward Neighbourhood Board, Chair Susan Wear (phase 1, plan submitted); Biddick Hall Pride in Place Neighbourhood Board, Chair Tracey Stephenson, Vice Chair Claire Finlay (phase 2, plan due 30 November 2026). [6,7,8]
  5. Development and delivery partners — Karbon Homes (extra care and supported living, Hebburn and South Shields); Miller Homes (198 homes, Westoe); Tyne Coast College / South Tyneside College (skills, and the college relocation funded by the Levelling Up Fund). [25,26,27,28,30]

Public routes for the next conversation

Enquiry Public route
National grant / finance enquiries@homesengland.gov.uk [1]
NECA housing / infrastructure 0191 211 5695; enquiries form at northeast-ca.gov.uk [see regions/north-east.md]
South Tyneside regeneration via southtyneside.gov.uk/article/1500/Regeneration; council contact centre 0300 123 6868 (general) [32]
Pride in Place (Jarrow, Biddick Hall) via southtyneside.gov.uk/jarrowforward and the Biddick Hall regeneration funding page [6,7]
Housing services / homelessness Housing Solutions Service, 0300 123 6633 [32]
Procurement South Tyneside Council via the NEPO Open portal (open-uk.org); procurement guidance at southtyneside.gov.uk/article/7071 [23,24]

A useful first enquiry names the site, landowner, proposed use, delivery lead, funding gap and next decision.

Accessing programme grant: a route for smaller providers

  • Continuous Market Engagement — Open for individual schemes and portfolios while funding remains available. [19]
  • Strategic partnerships — Programme-level allocations; the initial bidding round closed 15 April 2026; future rounds to be announced. [18]
Route Practical fit and requirements
CME general A direct scheme bid: eligible tenure, costs, delivery readiness and grant need with Homes England. [18,19]
CME portfolio Initial portfolios normally 300–500 homes; named sites start by 31 March 2028, complete by 31 March 2032. [19]
Delivery partnership An eligible RP or council can work with a strategic partner under the programme's delivery-partner rules. [18,20]

Organisations need Homes England Investment Partner qualification to receive grant. NECA's strategic priorities for the established mayoral strategic authority area set the shape of a bid: at least 60% Social Rent, economic-corridor and town/neighbourhood regeneration focus, low-carbon homes, council-led or community-led delivery. [21]

South Tyneside's adopted Local Plan (30 July 2026) sets a housing requirement of at least 5,253 homes over 2023–2040, phased at 180 homes a year for 2023–2028 and 363 homes a year for 2028–2040; the government's separate standard-method figure is 321 homes a year. The two figures are calculated differently and should not be netted against each other. The adopted Local Plan's own affordable-housing percentage by site was not retrieved for this brief — not verified. [17]

King Street, South Shields town centreIllustrative visualisation, AI-generated; adapted from a photograph by Peter Whatley, CC BY-SA 2.0

Places and programmes (borough programmes)

Westoe, South Shields — 198 homes

Miller Homes secured final Government planning approval on 25 March 2026 for 198 homes on the 9.3-hectare former South Tyneside College campus site, St George's Avenue, Westoe. The scheme generates a capital receipt reported at around £23m towards the college's relocation to South Shields town centre alongside the Marine School. Tenure mix and affordable-housing percentage were not itemised in the sources checked — open. [27]

Hebburn Extra Care — 96 homes

Karbon Homes, working with South Tyneside Council, is delivering a £26m extra care scheme of 96 homes (20 two-bed and 75 one-bed apartments, 17 of which are specialist dementia apartments — note the reported unit count exceeds 96 in the source and was not reconciled). Part of a wider three-scheme, up-to-300-home programme with the council. Homes England grant via Karbon's SAHP Strategic Partnership was referenced but not itemised to this scheme. [25]

South Shields Extra Care, Benton Road — 124 homes

Karbon Homes has started construction of a 124-home extra care scheme on the former Chuter Ede school and Ede Community Association site, Benton Road, South Shields. Completion date not verified in the sources checked. [26]

South Shields town centre and riverside — Levelling Up Fund, £20m

Round 3 Levelling Up Fund award of £20m supporting three projects: the relocation of South Tyneside College (Tyne Coast College) into South Shields town centre; a redeveloped Customs House and cultural quarter; and a Centre of Excellence at the Holborn Renewable Energy Network. Over £9m is reported for King Street and the market. Delivery status against these three strands was not itemised in the sources checked for this brief — open. [28]

Not reconciled with the above

The homes figures above are scheme-level and should not be summed with the Local Plan's 2023–2040 requirement of at least 5,253 homes, which already contains future supply from these and other sites. [17]

Grange Road, JarrowIllustrative visualisation, AI-generated; adapted from a photograph by Peter Whatley, CC BY-SA 2.0

Pride in Place: two neighbourhoods, two cohorts

South Tyneside has two Pride in Place neighbourhoods, each carrying its own up to £20 million over ten years and its own board. Do not sum the two into a single borough total.

Neighbourhood Phase (checked against the primary GOV.UK lists) Published position
Jarrow Phase 1 — named in MHCLG's phase 1 place-selection methodology note ("North East | South Tyneside | Jarrow"), among the original 75 phase 1 towns. No plan deadline applies. Up to £20m over ten years. The Jarrow Forward Neighbourhood Board, chaired by Susan Wear (Director, Southbank Communications), a partnership of 20 organisations, produced a ten-year Regeneration Plan after engaging more than 1,000 residents, 500 young people and 120 community groups, businesses, schools and service providers. Three stated priorities: better futures for young people; a re-energised town centre; a connected, cohesive community. The plan was submitted to Government in October 2025 with the support of Jarrow's MP Kate Osborne and the council; a "Jarrow Forward Fund" of small grants for local voluntary and community groups was due to launch November 2025. The council confirms the plan was approved by Government in April 2026, and publishes the document itself as the Jarrow Forward Jarrow Regeneration Plan 2026 to 2036. [7,8,9,10,33]
Biddick Hall Phase 2 — the phase 2 methodology note lists "South Tyneside | 1 | Biddick Hill" (the council's own page and press use "Biddick Hall"; the spelling is not reconciled between the two primary/secondary sources). Ten-year vision and four-year Investment Plan due 30 November 2026. Up to £20m over ten years, invested 2027–2037. Tracey Stephenson, a local resident with voluntary, community and business-sector experience, chairs the new Neighbourhood Board; Claire Finlay is Vice Chair. The Board's first meeting was expected September 2026. A series of resident engagement events has run; the Board will next agree specific regeneration projects, timescales, budget allocation and community benefits, for submission to Government in late 2026. The council states the programme's three core objectives as building stronger communities, creating thriving places and empowering local people. [6,11]

South Tyneside does not appear in the 20 March 2026 phase 2 expansion methodology note (40 neighbourhoods plus Wales): both South Tyneside areas were selected in earlier cohorts, so no third South Tyneside neighbourhood is expected from that list. [12]

Pride in Place Impact Fund — £750,000 in each of two years

South Tyneside appears in Annex A of both the 2025/26 determination and the 2026/27 determination at £750,000 a year — the standard rate applied to most of the 94 listed authorities each year. Do not add the two years together as if South Tyneside's ten-year Pride in Place grants were part of the same pot — the Impact Fund is separate money with its own borough-wide allocation and no published target wards found for this brief. [13,14]

Bring a project that can be delivered

  • Need, ownership and consent — Who benefits, land control, delivery lead, consents and dependencies.
  • Capital and continuing costs — Works, contingency, asset owner, operating budget and maintenance.

National delivery guidance requires each board to have at least eight members, with at least 51% living or working locally. [15,16]

Local investment and project calls: different pots, different decisions

Fund Amount Latest published position
Levelling Up Fund (round 3), South Shields town centre and riverside £20m College relocation, Customs House cultural quarter, Holborn Renewable Energy Network Centre of Excellence; over £9m reported for King Street and the market. Current spend status not verified. [28]
UK Shared Prosperity Fund £8.87m over three years Almost £8.8m awarded to date across 30 projects borough-wide. 2026/27 successor position for South Tyneside not verified in the sources checked. [29]
Pride in Place, Jarrow / Biddick Hall £20m each, ten years per neighbourhood See Pride in Place section above; two separate allocations, not a single sum. [6,7,11]
Pride in Place Impact Fund £750,000 a year for 2025/26 and 2026/27 Read directly from both GOV.UK determinations' Annex A. [13,14]
Brownfield Housing Fund (NECA) not verified No named South Tyneside award found in the sources checked for this brief — open. [see regions/north-east.md]

Do not add these figures together. They are different programmes, geographies and periods.

Houses on Victoria Road East, HebburnIllustrative visualisation, AI-generated; adapted from a photograph by JThomas, CC BY-SA 2.0

Homes, partners and local need

The Local Plan number

South Tyneside's Local Plan, adopted 30 July 2026, sets a housing requirement of at least 5,253 homes over 2023–2040: at least 180 homes a year for 2023–2028, then at least 363 homes a year for 2028–2040. Green Belt land at Fellgate was among the plan's most contentious housing allocations. The government's separate standard-method figure gives South Tyneside an indicative target of 321 homes a year; the two figures are calculated under different methods and should not be netted against each other. [17]

Named local delivery

Partner / example Documented local delivery
Miller Homes, Westoe 198 homes; final planning approval 25 March 2026; c.£23m capital receipt towards South Tyneside College's town-centre relocation. [27]
Karbon Homes, Hebburn Extra Care £26m, 96 homes (mixed one/two-bed, 17 dementia apartments); part of an up-to-300-home programme with the council. [25]
Karbon Homes, South Shields Extra Care (Benton Road) 124 homes on the former Chuter Ede school site; construction under way. [26]
Karbon Homes, supported living (Hedgeley Road; Nolan Hall, Jarrow) Bungalows and flats for supported/independent living, reported separately from the extra-care schemes above. [25]

One of the 33 first-wave SAHP strategic partners, Karbon Homes Limited (£350.0m of grant and 2,533 homes — the per-partner cap), is the borough's most active named delivery partner, but none of its South Tyneside schemes above is evidence of a South Tyneside-specific SAHP allocation: the partner table gives no site or borough breakdown. Karbon's own release describes the partnership as a consortium it leads with believe housing, Bernicia, Durham Aged Miners' Homes Association and Livin, which share those figures; GOV.UK names only "Karbon Homes Limited". Newcastle City Council is the only other North East entry; Home Group, Gentoo, Bernicia, believe housing and Thirteen are not in the table in their own right. [2,25,26,34]

Housing register and homelessness

South Tyneside Council's Housing Solutions Service (0300 123 6633) handles applications, homelessness prevention and South Tyneside Homes' independent-living (Housing Plus) stock. No current housing register total, band breakdown or homelessness presentation figures for South Tyneside were found in the sources checked — open. [32]

Delivery and the supply chain

Stage Lead organisations Specialist input
01 · Site and viability Council estates and regeneration, landowner, developer, RP, funders Land and planning advice, valuation, surveys, abnormal-cost assessment
02 · Enabling Council, developer, Homes England / NECA Ground investigation, remediation, ecology, civils, utilities
03 · Funding and agreement RP, developer, public funder, lender Legal, cost advice, programme and development finance
04 · Design and consent Client team, architect, South Tyneside planning authority Architecture, engineering, technical coordination
05 · Construction Main contractor and client delivery team Groundworks, structure, roofing, M&E, site services
06 · Handover and operation RP asset team, council or other operator Commissioning, landscaping, compliance, maintenance

Finding the actual route to work

South Tyneside Council advertises tenders through NEPO's Open portal (open-uk.org), which replaced the old NEPO Portal in February 2025 and is used by all North East local authorities, confirmed on the council's own "Selling to the Council and South Tyneside Homes" pages. Above-threshold notices also appear on Find a Tender (find-tender.service.gov.uk) and the Government's Contract Finder for opportunities over £25,000. [22,23,24]

Skills and delivery capacity

South Tyneside College, part of Tyne Coast College (formed by the 2017 merger of South Tyneside College, South Shields Marine School, Queen Alexandra Sixth Form College and Tyne Metropolitan College), delivers construction and built-environment provision across its campuses, alongside apprenticeships offered directly by the council and South Tyneside Homes (construction, ICT, HGV technician and other trades). [30,32]

The region's Construction Technical Excellence College is Sunderland College, hosting the Housing Innovation and Construction Skills Academy (HICSA) at Riverside Sunderland — one of ten CTECs named nationally on 12 August 2025. Tyne Coast College's role as a named spoke or delivery partner for HICSA was not confirmed in the sources checked for this brief — not verified; see regions/north-east.md for the region's full CTEC detail, which does not list a South Tyneside spoke college by name. [see regions/north-east.md, source 16]

Agree early What to record
Demand and timing Map labour needs to the programme
Employer and supervision Employing organisation, site supervisor, training partner
Learning and progression Qualification, practical experience, route into continuing work
Evidence of delivery How starts, completions and outcomes are recorded by the contract owner

Sources

Research checked on 19 September 2026.

  1. Homes England / National Housing Bank, Investment Prospectus 2026 · source
  2. Homes England / MHCLG, "Homes England and government confirm strategic partners...", 25 August 2026 (partner table: Newcastle City Council 966 homes/£141.4m; Karbon Homes Limited 2,533 homes/£350.0m nationally) · source
  3. MHCLG, "Historic council housebuilding comeback to help families into secure homes", 24 August 2026 — North East regional estimate £445m / c.3,400 homes · source
  4. South Tyneside Council, Biddick Hall regeneration funding · source
  5. South Tyneside Council, Jarrow regeneration · source
  6. South Tyneside Council, Jarrow Forward (Jarrow Neighbourhood Board) — Roles and membership · source
  7. Shields Gazette, "Jarrow Forward looks ahead to delivering £20million investment into the town" · source
  8. South Tyneside Council, "Ten-Year Regeneration Plan for Jarrow" (news, 29 October 2025) · source
  9. MHCLG, Pride in Place Programme phase 2: place selection methodology note ("South Tyneside | 1 | Biddick Hill") · source
  10. MHCLG, Pride in Place Programme phase 2 expansion: place selection methodology note, 20 March 2026 (no South Tyneside entry) · source
  11. MHCLG, Pride in Place Impact Fund grant determinations 2025–26 (Annex A: South Tyneside £750,000) · source
  12. MHCLG, Pride in Place Impact Fund grant determinations 2026–27 (Annex A: South Tyneside £750,000) · source
  13. MHCLG, Pride in Place programme delivery guidance · source
  14. MHCLG, Pride in Place programme prospectus · source
  15. South Tyneside Council / press reporting, South Tyneside Local Plan adoption (30 July 2026; 5,253 homes 2023–2040; 180/yr then 363/yr; Fellgate Green Belt allocations) · source · source · source
  16. Homes England, SAHP 2026–2036 guidance · source
  17. Homes England, Continuous Market Engagement route · source
  18. Homes England, Strategic Partnership route · source
  19. Homes England, SAHP strategic priorities in established mayoral strategic authority areas (NECA) · source
  20. Find a Tender service · source
  21. South Tyneside Council, Selling to the Council and South Tyneside Homes: Register your business · source
  22. NEPO, Open · source ; supplier registration · source
  23. Karbon Homes, "Partnership to bring new extra care facilities to South Tyneside" · source
  24. Housing Digital, "Karbon gets started on South Shields extra care scheme" · source
  25. Shields Gazette, "Government ruling sees South Shields 198-home scheme get final planning green light" · source
  26. South Tyneside Council, "£20m Funding Boost for South Shields Town Centre and Riverside" · source
  27. South Tyneside Council, UK Shared Prosperity Fund — Successful projects · source
  28. South Tyneside College, About TCC (Tyne Coast College) · source
  29. South Tyneside Council Housing Services, Contact us · source
  30. Jarrow Forward, Jarrow Regeneration Plan 2026 to 2036 (published by South Tyneside Council; plan approved by Government April 2026) · source
  31. Karbon Homes, North East housing providers form partnership to help deliver more social homes across the region (Karbon-led SAHP 2026–36 strategic partnership consortium with believe housing, Bernicia, Durham Aged Miners' Homes Association and Livin, sharing £350m / 2,533 homes) · source

For the regional routes ("in regions/north-east.md"), see the full numbered source list in that page's own Sources section (sources 1–25).

Research notes

Verified from primary sources

  • South Tyneside checked directly against all three primary GOV.UK Pride in Place lists: Jarrow confirmed phase 1 ("North East | South Tyneside | Jarrow" in the phase 1 methodology note); Biddick Hall confirmed phase 2 (listed as "South Tyneside | 1 | Biddick Hill" in the phase 2 methodology note — spelling not reconciled against the council's own "Biddick Hall"); neither appears in the 20 March 2026 phase 2 expansion note. [11,12]
  • Pride in Place Impact Fund checked directly against both determinations' Annex A: South Tyneside listed at £750,000 in both 2025/26 and 2026/27. [13,14]
  • SAHP first-wave partner table checked directly: South Tyneside Council is not a first-wave partner; Newcastle City Council and Karbon Homes Limited are the two North East entries; Karbon (£350.0m / 2,533 homes) is independently confirmed active on named South Tyneside schemes. Home Group, Gentoo, Bernicia, believe housing and Thirteen do not appear in the partner table in their own right, though four North East RPs sit inside Karbon's consortium. [2,25,26,34]
  • NEPO's Open portal confirmed as South Tyneside's procurement route from the council's own "Selling to the Council" pages, consistent with the regional page. [23,24]
  • Local Plan adoption date, housing requirement (5,253 homes, 2023–2040) and phasing read from council reporting and corroborated by local press. [17]

Not verified / press only

  • The Hebburn Extra Care unit breakdown (20 two-bed, 75 one-bed, 17 dementia apartments against a stated 96-home total) is inconsistent in the Karbon Homes source and not reconciled here.
  • Completion dates for the South Shields Extra Care scheme (Benton Road) and delivery status of the three Levelling Up Fund strands were not found.
  • South Tyneside's affordable-housing percentage by site in the adopted Local Plan, and any current housing register/homelessness presentation figures, were not found.
  • Tyne Coast College's role, if any, as a named HICSA spoke college is not confirmed; the regional page's own CTEC spoke-college list does not name it.

Open items

  • No named South Tyneside NECA Brownfield Housing Fund award was found (contrast with Northumberland, Gateshead and North Tyneside awards cited on the regional page).
  • The fifth-largest live scheme beyond the four named here was not searched; only four were researched against the 12-minute budget for this brief.
  • 2026/27 UK Shared Prosperity Fund successor position for South Tyneside is open.
  • Jarrow Forward and Biddick Hall board governance documents (terms of reference, accountable-body confirmation, quorum rules) were not retrieved in the depth applied to Wakefield's Featherstone board; only the council's public-facing pages and press were used.

Blocked or failed URLs

  • https://www.southtyneside.gov.uk/article/29257/Biddick-Hall-regeneration-funding — HTTP 403 to direct WebFetch; refetched successfully via ScrapingBee.
  • https://www.southtyneside.gov.uk/article/28667/Ten-Year-Regeneration-Plan-for-Jarrow — HTTP 403 to direct WebFetch; refetched successfully via ScrapingBee.

Verifier pass, 19 September 2026

  • Closed: Jarrow Forward's plan approval, previously marked not verified. The council confirms Government approval in April 2026 and publishes the Jarrow Forward Jarrow Regeneration Plan 2026 to 2036 itself; that document is now cited. [33]
  • Corrected: the SAHP paragraph now states what the partner table does and does not contain. Karbon Homes Limited's entry (2,533 homes, £350.0m) is the consortium's whole figure — Karbon's own release names believe housing, Bernicia, Durham Aged Miners' Homes Association and Livin as members, so the earlier flat statement that "Believe Housing ... do not appear in the partner table" needed the qualification that they sit inside Karbon's entry rather than outside the programme. Newcastle City Council remains the only other North East entry. [2,34]
  • Confirmed unchanged, re-checked against the three GOV.UK lists: Jarrow is phase 1 ("North East | South Tyneside | Jarrow" among the 75 towns) with no plan deadline; Biddick Hall is phase 2, entered as "South Tyneside | 1 | Biddick Hill", plan due 30 November 2026; South Tyneside is absent from the 20 March 2026 expansion list. The Biddick Hill / Biddick Hall spelling difference is real and stays flagged.
  • Confirmed unchanged: Impact Fund £750,000 in each of 2025/26 and 2026/27 from Annex A of both determinations (93 of 94 authorities at that rate each year; only Bridgend at £1,500,000); the adopted Local Plan (30 July 2026, at least 5,253 homes 2023–2040, 180/yr then 363/yr, standard method 321/yr); Open (NEPO) as the procurement portal from the council's own pages; board chairs Susan Wear and Tracey Stephenson with Vice Chair Claire Finlay.
  • Still open, and what was searched: no named South Tyneside NECA Brownfield Housing Fund award (NECA news and delegated decision reports name Gateshead, North Tyneside, Northumberland and Sunderland schemes, not South Tyneside); the adopted Local Plan's affordable-housing percentage by site; the Hebburn Extra Care unit breakdown, which is internally inconsistent in Karbon's own source; Levelling Up Fund strand delivery status and the 2026/27 UKSPF successor position; housing register and homelessness figures; Tyne Coast College as a named CTEC spoke.

General information only, not legal, financial or professional advice. Confirm eligibility and terms with the relevant body.