Funding, places and delivery. A briefing for the organisations bringing forward homes and regeneration across Walsall, Darlaston, Bloxwich, Willenhall and Aldridge-Brownhills.

Dates and decisions to watch
| As at 19 September 2026 | Published position |
|---|---|
| Walsall Borough Local Plan | Regulation 19 (publication stage) consultation launches Monday 21 September 2026, running six weeks to 2 November 2026; an earlier 14 September start date reported in council coverage was revised. Government requires submission by 31 December 2026, adoption targeted 2027. [7,8] |
| Blakenall South Pride in Place | Phase 2. £20m over ten years, announced 30 October 2025; independent chair applications closed 18 August 2026; Pride in Place Plan due to government for assessment by 30 November 2026; funds released from Spring 2027 at the earliest. [9,10,11] |
| Darlaston Pride in Place | Phase 1, confirmed on MHCLG's phase 1 methodology note ("West Midlands | Walsall | Darlaston"). £20m over ten years; Board chaired by Manjit Jhooty met for the first time 9 October 2025; a rival community-led board (chaired by Joyce Gibson) disputes the council's process — not resolved. Phase 1 places have had their capacity funding and are in year 1 of delivery: the national timeline sets no plan deadline against them. [12,13,14,56] |
| Brownhills Pride in Place (phase 2 expansion) | Walsall's third Pride in Place place, previously missing from this brief. Named on MHCLG's phase 2 expansion list published 20 March 2026 ("Walsall | 1 | Brownhills"); £20m over ten years, £2m a year. Pride in Place Plan due to MHCLG by 26 February 2027, the deadline for the 40 places named in March 2026 — note that council and press coverage of the announcement said "November 2026", which matches the earlier phase 2 cohort, not this one. Board arrangements not yet published — not verified. [41,57] |
| Willenhall / Moat Street (Locksmiths Quarter) | Demolition of six brownfield sites began January 2026; Keepmoat Homes is development partner; not verified how many of the c.100–111 homes have started on site as at 19 September 2026. [15,16] |
| Pride in Place Impact Fund | £750,000 determined 29 September 2025 (2025/26) and £750,000 determined 8 April 2026 (2026/27), £1.5m total; national guidance requires commitment by 31 March 2027. [17,45,46] |
Figures in this briefing cover different programmes, geographies and periods. They should not be added into a single borough investment total.
The funding landscape
Up to £46 billion over ten years
Homes England and its subsidiary, the National Housing Bank, have up to £46 billion to deploy across England to 2036. These are the principal streams. [1]
The joint Investment Prospectus, published on 31 March 2026 ahead of the Bank's opening on 1 April, brings grant, land and finance into one framework. The Bank aims to attract more than £50 billion of additional private capital over the decade.
| Stream | Amount | What it funds / who it reaches |
|---|---|---|
| Social and Affordable Homes Programme 2026–2036 | At least £27bn outside London; £39bn nationally, including London | Capital grant for social and affordable rent, shared ownership, supported housing and estate regeneration. Registered Providers, councils, housebuilders and community-led organisations, through continuous market engagement or strategic partnerships. |
| Housing and Infrastructure Capital Grant | About £3.1bn (Homes England's share of the £5bn national pot*) | Land assembly, remediation and strategic infrastructure; dedicated viability-gap support planned for later in 2026/27. Councils, developers and landowners with sites the market cannot unlock alone. |
| National Housing Delivery Fund (debt, equity and guarantees) | Up to £16bn | Loans, equity and guarantees, including funding that may be devolved to mayoral authorities. Housebuilders, Registered Providers, funds and lending partners. |
*The prospectus describes the agency's share as £3.1bn, subject to final confirmation. These are programme envelopes, not a ring-fenced allocation to Walsall.
Programme milestones
| Date | Milestone |
|---|---|
| 31 March / 1 April 2026 | Investment Prospectus published / National Housing Bank opens |
| 24 August 2026 | MHCLG publishes a regional funding breakdown estimating the West Midlands' first-wave Strategic Partnership spend at £409m / c.3,200 homes — a regional estimate, not a Walsall award [59] |
| 25 August 2026 | First wave: 33 strategic partners confirmed outside London. The Homes England release states no grant or homes total; its partner table sums to £9,584.1m and 73,617 homes, each partner capped at £350.0m. No West Midlands or Walsall figure is given in that release [2] |
| Later in 2026/27 | Dedicated viability-gap grant planned [1] |
| To 2036 | Ten-year programme period |
Grant, land and finance (products and routes)
Which support fits a scheme depends less on its size than on what is holding it up: a funding gap, a difficult site, or the tenure of the homes to be delivered. [1]
| Family | Product | Purpose | Typical user |
|---|---|---|---|
| Grant | Social and Affordable Homes Programme | Affordable tenures, supported housing and estate regeneration | RPs, councils, developer partners |
| Grant | Housing and Infrastructure Capital Grant | Viability gaps, infrastructure, land assembly and remediation | Councils, landowners, master developers |
| Land | Homes England land | Acquisition, enabling and disposal through sale, lease, development agreement or joint venture | Developers of all sizes |
| Finance | SME Accelerator Loan | Site finance for smaller builders establishing a track record | SME housebuilders |
| Finance | Revolving credit facility | Multi-site support alongside commercial lenders | Growing builders |
| Finance | Senior and mezzanine debt | Project funding for build to rent, later living and brownfield schemes | Developers and funds |
| Finance | Corporate lending | Balance-sheet finance for growth, including modern methods of construction | Housebuilders |
| Finance | Infrastructure loans | Long-term finance, up to 15 years, for upfront infrastructure | Developers and councils |
| Finance | Low-interest RP loans | Unlocking capital investment in social and affordable homes | Registered Providers |
| Finance | Equity | Minority investment in vehicles typically delivering more than 3,000 homes | Funds and partnerships |
| Finance | Guarantees | Bonds and loans to reduce institutional financing costs | Funds and RPs |
Two grant routes in the West Midlands. Housing and infrastructure grant is normally expected to come first through WMCA's integrated settlement. Social and Affordable Homes Programme grant remains administered by Homes England. The National Housing Bank makes its own finance decisions while working alongside the agency. [1,32]
West Midlands: how the regional routes fit together
Regional routes: see regions/west-midlands.md for WMCA's devolved housing and land funds, the integrated settlement, the Birmingham East Mayoral Development Corporation, the Spatial Development Strategy, the SAHP first-wave regional estimate (MHCLG's published £409m / c.3,200 homes) and the regional skills offer.
For a Walsall scheme, the first conversation depends on the funding gap. A regional headline figure is not a borough award; the Homes England SAHP first-wave release of 25 August 2026 gives no West Midlands figure of its own. MHCLG's separate release of 24 August 2026 does publish a West Midlands regional estimate — £409m / c.3,200 homes — but this too is a regional estimate, not a borough award, and does not break down to Walsall. [2,59]
| Scheme requirement | Route to establish (Walsall) | What to resolve |
|---|---|---|
| Social and affordable homes | Homes England's SAHP 2026–2036, through strategic partnership or continuous market engagement, shaped by WMCA's published mayoral strategic priorities. | Tenure mix against the mayor's approximately 60% Social Rent priority; delivery partner; grant requirement and timing. [18,21] |
| Land, infrastructure or abnormal costs | Walsall Council (Regeneration and Investment) with WMCA's devolved housing and land funds, via the Single Commissioning Framework; Homes England Housing and Infrastructure Capital Grant. | Why the site cannot proceed, what intervention unlocks it, whether it sits on the Walsall–Wolverhampton growth corridor. [3,33] |
| Additional affordable-housing support | WMCA housing and regeneration team, via the integrated settlement. | SAHP should be secured or actively progressing; explain the remaining gap and deliverability. [50] |
| Debt, equity or guarantees | National Housing Bank via Homes England; WMCA's Residential Investment Fund or Commercial Investment Fund for smaller revolving loans. | Borrower or investment structure, commercial funding, security and the route to repayment. [1,2] |
The Walsall to Wolverhampton growth corridor. Walsall's own 2020–2025 Housing Strategy names this corridor — stretching from Walsall town centre to Wolverhampton city centre via M6 Junction 10, Birchills, Leamore and Willenhall — as a priority regeneration area within the 2018 Housing Deal, with an ambition of approximately 8,500 homes across the corridor by 2031, many within the Walsall boundary. [24] This is a corridor-wide ambition from a now-dated strategy document, not a live Walsall award; the regional routes page describes the successor Wolverhampton Green Innovation Corridor and floats a possible second Mayoral Development Corporation on the same alignment, not yet established. [33]
Regional ambitions to design for
WMCA's Growth Plan seeks 120,000 homes over the decade to c.2035 and 20,000 social and affordable homes over the next decade region-wide, with a mayoral tenure ambition of approximately 60% Social Rent in SAHP bids. These are seven-borough totals, not a Walsall figure. [33]
Who decides what (decisions and public contacts)
- Homes England / National Housing Bank — Final SAHP funding and contractual decisions; the Bank assesses its finance investments. [1,18]
- West Midlands Combined Authority — Regional priorities, tenure mix; devolved housing and land funds; integrated settlement; Spatial Development Strategy. [3,50]
- Walsall Council — Local housing need, planning authority, council land and CPO powers; accountable body for Pride in Place (Darlaston and Blakenall South) and the Impact Fund; joint applicant with development partners at Willenhall. [9,12,15,16]
- Darlaston Town Board and the Blakenall South neighbourhood board — Shape and sign off the two Pride in Place plans; council accountability and national programme rules still apply. A rival, community-organised Darlaston board (chaired by Joyce Gibson) disputes the council-appointed board's legitimacy — not resolved. [12,13,14]
- Development partners under contract — Keepmoat Homes at Willenhall/Moat Street; Anthem Lovell (the Lovell/whg joint venture) at Lockside and the former Metafin site. These are existing appointments, not open opportunities. [15,22,23]
- Registered Providers — whg (walsall housing group, c.20,000 homes, the borough's largest landlord since the 2003 stock transfer), WATMOS (c.1,700 homes) and Longhurst Group/Beechdale (c.1,300 homes) together own about 80% of Walsall's affordable housing; Accord Housing Association (c.4,200 homes) is the other main provider. [24]
Public routes for the next conversation
| Enquiry | Public route |
|---|---|
| National grant / finance | enquiries@homesengland.gov.uk [1] |
| WMCA investment pre-application | invest@wmca.org.uk [3] |
| Walsall regeneration and investment | 01922 654747 · 2nd Floor, Civic Centre, Darwall Street, Walsall WS1 1DG [25] |
| Planning policy / Local Plan | Walsall Council planning policy team, via go.walsall.gov.uk Local Plan pages [7] |
| Housing strategy | Walsall Council housing service, via go.walsall.gov.uk/housing [26] |
| Pride in Place, Darlaston | Darlaston Plan board · darlastonplan.co.uk [13] |
| Pride in Place, Blakenall South | Walsall Council, via the council's Pride in Place newsroom pages [9] |
| Procurement | Walsall Council procurement, 01922 658471 · in-tendhost.co.uk/walsallcouncil [29] |
A useful first enquiry names the site, landowner, proposed use, delivery lead, funding gap and next decision.
Accessing programme grant: a route for smaller providers
- Continuous Market Engagement — Open for individual schemes and portfolios while funding remains available. Designed to accommodate smaller partners, new entrants and complex projects. [19]
- Strategic partnerships — Programme-level allocations. The initial bidding round closed on 15 April 2026; future rounds will be announced. [18]
| Route | Practical fit and requirements |
|---|---|
| CME general | A direct scheme bid. Establish eligible tenure, costs, delivery readiness and grant need with Homes England. [18,19] |
| CME portfolio | Initial portfolios normally deliver 300–500 homes; named sites should start by 31 March 2028 and complete by 31 March 2032. [19] |
| Delivery partnership | An eligible RP or council can work with a strategic partner under the programme's delivery-partner rules. [18,20] |
Before a grant application
Organisations need Homes England Investment Partner qualification to receive grant. WMCA's published mayoral strategic priorities for SAHP bids in the seven boroughs seek approximately 60% Social Rent, alongside Stepping Stone supportive accommodation, wheelchair-accessible M4(3) homes and estate regeneration. [21]
Walsall's own emerging position is a "brownfield first" approach: the adopted Site Allocation Document (January 2019) and the 2020–2025 Housing Strategy record a standard-method need of 908 net new homes a year against roughly 734 a year actually delivered over the preceding five years — a gap the current Local Plan process is now trying to close at borough scale. [8,27]

Places and programmes (borough programmes)
Lockside, former Caparo Engineering works — 252 homes, under construction
Anthem Lovell (the joint venture between Anthem, whg's development subsidiary, and Lovell) is building 252 homes on the former Caparo steelworks site, roughly a mile from Walsall town centre: one, two, three and four-bedroom homes, with 132 for open market sale through Lovell Homes and 120 taken by whg for affordable rent, shared ownership and a 50-home wellbeing scheme for over-55s. The scheme is branded Lockside. whg has completed the first phase of homes; press reporting describes a £44m investment. [22,30,31]
Metafin site, Walsall town centre canalside — 72 homes, under construction
A second Anthem Lovell site, on the former Metafin works, is delivering a further 72 homes for affordable rent, described by the partners as part of the same wider canalside regeneration programme as Lockside. Press coverage sums the two sites to 324 homes; treat Lockside (252) and Metafin (72) as separate consents, not a single scheme. [22,23]
Hollyhedge Lane, whg — 71 social rent homes, £1m WMCA grant
West Midlands Mayor Richard Parker announced £1m of WMCA funding in February 2026 to unlock a stalled scheme on the former scrapyard site at Hollyhedge Lane. The completed scheme will deliver 71 social rent homes, owned and managed by whg, with Lovell Partnerships appointed to build. The council and whg describe the scheme as previously delayed; the £1m is intended to kickstart it. [34]
Willenhall / Moat Street "Locksmiths Quarter" — around 100–111 homes, demolition under way
Walsall Council used compulsory purchase powers to assemble land across six brownfield sites between Villiers Street, Moat Street/Newhall Street and Stafford Street/Temple Bar. Keepmoat Homes Ltd was appointed development partner in November 2023 following competitive procurement. Outline planning permission granted 16 July 2024 covers 107 homes (54 apartments, 53 houses); other council and press figures cite "around 100" or "111" homes for the same programme — treat 107 as the outline-permission figure and the others as rounded press figures, not additional homes. Demolition of the first sites, supported by AR Demolition, began January 2026; site surveys and asbestos removal ran through late 2025. Funding is a successful £20m Levelling Up Fund Round 2 bid (Walsall North, announced January 2023), described by government and the council as unlocking a wider £210m Willenhall Garden City regeneration plan including new homes, parks and a new railway station; a separate £19m Walsall South LUF2 bid for a town-centre theatre was unsuccessful. [15,16,35,43,44]
Walsall town centre masterplan — context, not a single scheme
The wider Walsall Town Centre Masterplan is described by the council as a £1.5bn programme aiming to create more than 4,000 jobs and over 1,000 new homes across the town centre over 20 years; do not add this figure to the four schemes above, several of which sit inside or adjacent to the masterplan area. The Connected Gateway Project, funded by an £11.4m Future High Streets Fund award secured in 2021 plus council match funding, is delivering the current phase: refurbishment of the Saddlers Centre (ground-floor works completed October 2025, with the former M&S unit becoming a Walsall College adult-learning facility) and improved walking routes between the railway station, the mall and the bus station. [36,37,38]
Completed context
Walsall's 2020–2025 Housing Strategy records recent completions including 412 homes at Waterskeep, 235 homes in Brownhills district centre, 233 homes at The Woodlands, Moxley, 170 homes on the former Servis site in Darlaston, and the historic Walsall Waterfront scheme by Accord Housing Association — 322 mixed-tenure homes on a 5.5-acre canalside site, including 68 homes for Walsall Manor Hospital key workers and an NHS-let midwifery-led birthing centre, funded with a £15m Homes and Communities Agency grant. These are delivered, not pipeline; the Accord scheme in particular dates from the Homes and Communities Agency era, before Homes England's creation. [24,39]

Pride in Place: three places, three cohorts, one dispute
Walsall has one place in each of the programme's three national cohorts, and the previous edition of this brief carried only two of them: Darlaston (phase 1, board meeting since October 2025), Blakenall South (phase 2, plan due 30 November 2026) and Brownhills (phase 2 expansion, named 20 March 2026, plan due 26 February 2027). National guidance sets different milestones for each; they must not be approached the same way, and the three £20m awards must never be summed. [40,41,56,57]
| Neighbourhood | Published position / next conversation |
|---|---|
| Darlaston (phase one) | £20m over ten years, inherited from the 2024/25 Plan for Neighbourhoods programme. Council-recognised board chaired by independent chair Manjit Jhooty (also chair of the Walsall and Bloxwich Towns Fund board), met for the first time 9 October 2025; 69% of voting members live or work in Darlaston. Correction to the previous edition: there is no 26 February 2027 deadline for Darlaston. That date in the delivery guidance applies to the 40 phase 2 places named in March 2026 and to phase 2 places in Wales, not to phase 1. The guidance states that phase 1 places "have received their early capacity funding and are now in year 1 of delivery" and sets no further plan deadline against them; Darlaston's plan obligations run through its existing Plan for Neighbourhoods documentation. A rival, community-organised board chaired by Joyce Gibson disputes the legitimacy of the council's chair appointment and the lack of public involvement in selecting it — unresolved as at 19 September 2026. [12,13,14,41,56] |
| Blakenall South (phase two) | £20m over ten years, announced 30 October 2025; the target area runs from Bloxwich Road through Harden, homes south of Well Lane and the Wyrley View estate off Goscote Lane. Cabinet on 18 March 2026 tasked officers with appointing the neighbourhood board; applications for an independent chair closed 18 August 2026; no appointment confirmed in council sources as at 19 September 2026 — not verified. The Pride in Place Plan is due to government for assessment by 30 November 2026, with funds released "from as early as Spring 2027." Confirmed against MHCLG's phase 2 place-selection note, which lists Walsall's single original phase 2 neighbourhood as Blakenall South. [9,10,11,42] |
| Brownhills (phase 2 expansion) | £20m over ten years, £2m a year. Named on MHCLG's phase 2 expansion place-selection methodology note published 20 March 2026 ("Walsall | 1 | Brownhills"), one of 40 neighbourhoods added nationally that day. Under the expansion's own selection rules, an MSOA in a parliamentary constituency that already held a phase 1 or phase 2 place was excluded — which is why Brownhills sits in Aldridge-Brownhills rather than alongside Darlaston or Blakenall. The board will decide how the money is spent; no chair or board membership has been published as at 19 September 2026 — not verified. Plan due to MHCLG by 26 February 2027. Council and press coverage of the announcement quoted a November 2026 deadline; that is the phase 2 date, not the expansion cohort's. [41,57] |
Bring a project that can be delivered
- Need, ownership and consent — Who benefits, land control, delivery lead, consents and dependencies.
- Capital and continuing costs — Works, contingency, asset owner, operating budget and maintenance.
National guidance sets 30 November 2026 for the 160 original phase 2 boards (Blakenall South) and 26 February 2027 for the 40 boards in places named in March 2026 (Brownhills). It sets no plan milestone for phase 1 areas (Darlaston), which are already in year 1 of delivery. Boards must have at least eight members; at least 51% should live or work locally. Phase 2 areas received £150,000 early revenue funding in 2025/26 and a further £135,000 revenue plus £117,604 capital in 2026/27; £1.36m follows in 2027/28 once the Plan is approved. [40,41]
Local investment and project calls: different pots, different decisions
| Fund | Amount | Latest published position |
|---|---|---|
| Pride in Place, Darlaston | £20m over ten years | Phase 1; board meeting since 9 October 2025; delivery already under the earlier Plan for Neighbourhoods branding. No further national plan deadline applies. [12,13,41,56] |
| Pride in Place, Brownhills | £20m over ten years | Phase 2 expansion, named 20 March 2026; Plan due 26 February 2027; board arrangements not yet published. [41,57] |
| Pride in Place, Blakenall South | £20m over ten years | Board chair applications closed 18 August 2026; Plan due to government by 30 November 2026; funds from Spring 2027 at the earliest. [9,10,11] |
| Pride in Place Impact Fund | £1.5m (£750,000 in 2025/26, £750,000 in 2026/27) | Determinations of 29 September 2025 and 8 April 2026. Council states funding will be "split between a number of wards" across three themes — high street/town centre revitalisation, public spaces and community spaces — informed by consultation with voluntary and community sector organisations and the borough's MPs. No individual ward allocations published. [17,45,46,47] |
| Levelling Up Fund Round 2, Willenhall (Walsall North) | £20m | Successful bid announced January 2023; funds land acquisition and enabling works for c.107–111 homes at Moat Street/Villiers Street, part of a wider £210m Willenhall Garden City plan; demolition under way from January 2026. [15,43,44] |
| Levelling Up Fund Round 2, Walsall South (theatre) | £19m bid | Unsuccessful; no theatre scheme secured through this route. [43,44] |
| Bloxwich and Walsall Towns Fund | £42.6m government funding (c.£66m with match and external funding) | Eleven approved projects across Bloxwich and Walsall town centre, including a Construction Skills Academy, Digital Skills Hub, Creative Industries Enterprise Centre and Adult Learning Campus; not primarily a housing fund. [48,49] |
| Future High Streets Fund, Walsall Connected Gateway | £11.4m, secured 2021 | Delivering early phases of the Town Centre Masterplan: Saddlers Centre refurbishment (ground floor complete October 2025) and station-to-bus-station walking route improvements. [37,38] |
| WMCA housing and land funds (Brownfield Land and Property Development Fund, Revolving Investment Fund, Collective Investment Fund) | Regional envelopes, not Walsall-specific | Used to fund the original £787,000 Walsall Waterfront/House by Urban Splash canalside scheme (2021) and the £1m Hollyhedge Lane award (2026); confirm current live status with WMCA. [3,34,39] |
| UK Shared Prosperity Fund | £8,252,409 (to March 2025) | Programme wound down; successor Local Growth Fund / Pride in Place funding from April 2026 administered through WMCA's integrated settlement. No Walsall-specific 2026/27 allocation figure found — not verified. [26,50] |
Do not add these figures together. They are different programmes, geographies and periods, and some of them fund overlapping sites.

Homes, partners and local need
What the evidence base says
Walsall's 2020–2025 Housing Strategy, "Delivering new and improved homes for the people of Walsall," is the most recent adopted strategy read directly for this briefing; a successor Walsall Borough Housing Strategy to 2040 was out for consultation from 15 December 2025 to 26 January 2026 and its adoption status is not verified as at 19 September 2026. [26,51]
| Measure | Figure |
|---|---|
| Standard-method housing need (2017 evidence) | 908 net new homes a year [27] |
| Average homes actually delivered, preceding five years | 734 a year [27] |
| Government-set housing requirement now driving the new Local Plan | 21,026 homes [8] |
| Homes allocated in the draft (Reform-authored) Local Plan | 14,943 homes, a shortfall of 6,083 [8] |
| Green Belt sites in the draft allocation | Nine sites, over 5,000 homes, two within the Great Barr Conservation Area [8] |
| Gypsy and Traveller / Travelling Showpeople provision (2019 Site Allocation Document) | 66 Gypsy and Traveller pitches, 90 Travelling Showpeople plots [27] |
Treat the 908-a-year figure as the 2020 strategy's evidence base and the 21,026/14,943 figures as the current (September 2026) Local Plan position; they come from different evidence rounds eight years apart and should not be read as the same number restated. [8,27]
Who owns the borough's affordable homes
Walsall Council transferred its housing stock in 2003 to whg (walsall housing group) and WATMOS (Walsall Association of Tenant Management Organisations), following an earlier 1996 transfer to Beechdale Housing Association, now part of Longhurst Group. Approximate current stock: whg 20,000 homes, WATMOS 1,700, Longhurst/Beechdale 1,300 — together about 80% of the borough's affordable housing. Accord Housing Association holds a further c.4,200 homes. Smaller numbers are held by Bromford, Clarion, Midland Heart, PA Housing and Stonewater, with older-person housing from Housing 21, Hanover and Nehemiah. Most of these providers sit together with the council on the Walsall Housing Partnership. [24]
Named local delivery
| Partner / example | Documented local delivery |
|---|---|
| Anthem Lovell (whg / Lovell joint venture) / Lockside, former Caparo works | 252 homes, mixed tenure, first phase complete; £44m scheme. [22,30,31] |
| Anthem Lovell / former Metafin site | 72 homes for affordable rent, under construction. [22,23] |
| whg / Lovell Partnerships / Hollyhedge Lane | 71 social rent homes; £1m WMCA grant announced February 2026 to unlock a previously stalled scheme. [34] |
| Keepmoat Homes / Willenhall, Moat Street and Villiers Street | 107 homes under outline permission (54 apartments, 53 houses); demolition under way from January 2026; £20m LUF2 grant. [15,16,35,43] |
| Accord Housing Association / Walsall Waterfront | 322 mixed-tenure homes, delivered; £15m Homes and Communities Agency grant; historic scheme, not pipeline. [39] |
Seven SAHP first-wave strategic partners have a substantial West Midlands presence — Midland Heart, Platform, Bromford Flagship Livewest, Orbit, Sanctuary, Places for People and Vistry — but the 25 August 2026 Homes England release names no Walsall allocation for any of them; whg and Accord, the borough's two largest landlords, are not on the 33-partner list, so their route into the new programme is continuous market engagement or a delivery partnership. [2,18,24]
These are examples of local activity, not a complete provider list or evidence of a new SAHP award.
Delivery and the supply chain
| Stage | Lead organisations | Specialist input |
|---|---|---|
| 01 · Site and viability | Council estates and regeneration, landowner, developer, RP, funders | Land and planning advice, valuation, surveys, abnormal-cost assessment |
| 02 · Enabling | Council, developer, Homes England / WMCA | Ground investigation, remediation, ecology, civils, utilities |
| 03 · Funding and agreement | RP, developer, public funder, lender | Legal, cost advice, programme and development finance |
| 04 · Design and consent | Client team, architect, Walsall planning | Architecture, engineering, technical coordination |
| 05 · Construction | Main contractor and client delivery team | Groundworks, structure, roofing, M&E, site services |
| 06 · Handover and operation | RP asset team, council or other operator | Commissioning, landscaping, compliance, maintenance |
Finding the actual route to work
Walsall Council runs its own In-tend instance — not a shared regional portal — at in-tendhost.co.uk/walsallcouncil. Suppliers register free to view current and future opportunities, express interest and exchange tender documents; the procurement team can be reached on 01922 658471 for problems during a submission. Above-threshold notices also appear on Find a Tender; below-threshold notices on Contracts Finder and the council's own portal. [29,52]
The council publishes a Contracts Register listing current contracts, separate from the live tender portal; the most recent published version seen for this briefing is dated July 2024, so it should be treated as a snapshot rather than a live pipeline document. [53]
Social value. Walsall's published Social Value Policy applies the Public Services (Social Value) Act 2012 across applicable contracts, with stated objectives to promote equity by targeting effort towards those in greatest need and to promote the local economy so that micro, small and medium enterprises and the borough's voluntary and community sector can thrive. No single published percentage weighting was found; establish it per tender. [54]
A funding announcement does not itself create an open invitation to tender. At Lockside, Metafin and Hollyhedge Lane the delivery partner (Anthem Lovell / Lovell Partnerships) and at Willenhall the development partner (Keepmoat Homes) are already appointed; supply-chain work on those schemes flows through those partners, not through a council tender.
Skills and delivery capacity
Walsall College is the borough's further education provider, with construction and the built environment taught from its Green Lane campus. Published provision includes the Construction Gateway — 20 days of training in groundwork, trowel operations, plastering, dry lining and carpentry with a guaranteed job interview — plus Level 2 and higher construction courses and apprenticeships, some delivered through the college's Construction College Midlands site in Birmingham. The college is a partner in the Town Centre Masterplan's Saddlers Centre works, which include a new adult-learning facility. General enquiries: info@walsallcollege.ac.uk. [55,37]
The region's Construction Technical Excellence College is hosted by Dudley College of Technology, one of ten such colleges in England, announced 12 August 2025 with £100m of national funding (£80m capital, £20m revenue across all ten colleges); its remit covers the seven WMCA boroughs including Walsall, delivered from the Construction Apprenticeship Training Centre in Brierley Hill and the Advance Centre in Dudley. Employer contact 01384 363 000 · dudleycol.ac.uk/employers/. See regions/west-midlands.md for the CTEC's full scope. [58]
Walsall's own housing strategy sets a five-year target — now several years into its life — of helping to create 50 construction apprenticeships and 100 pre-employment traineeships through the council's Walsall Works team working with developers and Registered Providers via the planning process. Whether this target has been met is not verified. [27]
| Agree early | What to record |
|---|---|
| Demand and timing | Map labour needs to the programme |
| Employer and supervision | Employing organisation, site supervisor, training partner |
| Learning and progression | Qualification, practical experience, route into continuing work |
| Evidence of delivery | How starts, completions and outcomes are recorded by the contract owner |
Sources
Research checked on 19 September 2026.
- Homes England / National Housing Bank, Investment Prospectus 2026 · source
- Homes England / MHCLG, SAHP first-wave strategic partners, 25 August 2026 · source
- WMCA, Investing with us (Single Commissioning Framework, funds, invest@wmca.org.uk) · source
- Walsall Council, "Next phase of the Walsall Borough Local Plan consultation to launch next month" · source
- Express & Star, "Reform to 'press for flexibility' with huge housing targets in Walsall" · source
- Walsall Council, "Blakenall to benefit from £20 million in Government Pride in Place funding" · source
- Express & Star, "'It would be wrong not to welcome' £20million government boost for Walsall neighbourhood, council leader says" · source
- MHCLG, Pride in Place programme delivery guidance · source
- Express & Star, "'Locals know best' – Fallout over £20m spending in Darlaston continues as board set up" · source
- Darlaston Plan, "About the Board" · source
- Express & Star, "'We've been taken for fools': Darlaston residents on rival £20m spending board criticise council" · source
- Invest Walsall, "Demolition starts in Willenhall as council drives forward plans for new homes" · source
- Walsall Council, "Council's intervention to turn derelict Willenhall sites into housing" · source
- MHCLG, Pride in Place Impact Fund grant determinations 2025–26 · source
- Homes England, SAHP 2026–2036 guidance · source
- Homes England, SAHP Continuous Market Engagement route · source
- Homes England, SAHP Strategic Partnership route · source
- Homes England, SAHP 2026–2036: strategic priorities in established mayoral strategic authority areas · source
- Housing Digital, "whg completes first phase of 252-home development in Walsall" · source
- Housing Digital, "whg gets 72-home canalside development underway in Walsall" · source
- Walsall Council, Housing Strategy 2020–2025, "Delivering new and improved homes for the people of Walsall" · source
- Walsall Council, Regeneration and investment (contact) · source
- Walsall Council, UK Shared Prosperity Fund (UKSPF) · source
- Walsall Council, Housing Strategy 2020–2025 (same document as source 24, read for the standard-method need and target figures) · source
- Walsall Council, procurement · source ; portal source
- Express & Star, "Work continuing on major £44 million housing development in Walsall" · source
- The Construction Index, "House building starts on old Caparo steelworks site" · source
- MHCLG, written ministerial statement on Integrated Settlements, 30 January 2025 (HCWS405) · source
regions/west-midlands.md— this briefing's companion regional routes page (WMCA housing/land funds, growth corridors, Growth Plan ambitions) · source- Express & Star, "£1m boost to kickstart delayed Walsall housing scheme" · source
- Place Midlands, "Decision due on Keepmoat's Willenhall regen plans" · source
- Place Midlands, "Walsall regeneration: Here's what's coming in 2026" · source
- TheBusinessDesk.com, "Designs revealed for £11m overhaul of Walsall town centre" · source
- Walsall Council, Walsall Town Centre Masterplan: Connected Gateway Project · source
- Inside Housing, "Accord Group: Walsall Waterfront, Walsall" · source
- MHCLG, Pride in Place programme prospectus · source
- MHCLG, Pride in Place programme delivery guidance (phase milestones) · source
- MHCLG, Pride in Place programme phase 2 methodology note ("Walsall | 1 | Blakenall South") · source
- GOV.UK case study, "£20 million awarded to Walsall to transform Willenhall — Levelling Up Fund 2" · source
- Walsall Council, "Levelling [Up] Fund bid successfully secures £20m to transform Willenhall" · source
- MHCLG, Pride in Place Impact Fund grant determinations 2026–27 · source
- Walsall Council, "Borough of Walsall to benefit from £1.5million boost" · source
- MHCLG, Pride in Place Impact Fund frequently asked questions · source
- Walsall Council, "About the Town Deal" · source
- Walsall Council, Town Deal funded projects · source
- WMCA, Integrated Settlement: what the funding means for the West Midlands · source
- Walsall Council, "Residents invited to have their say on Walsall's future housing strategy" · source
- Find a Tender service · source
- Walsall Council, Contracts Register, July 2024 · source
- Walsall Council, Social value · source
- Walsall College, Construction and the Built Environment courses · source
- MHCLG, Pride in Place Programme phase 1: place selection methodology note ("West Midlands | Walsall | Darlaston") · source
- MHCLG, Pride in Place Programme phase 2 expansion: place selection methodology note, published 20 March 2026 ("Walsall | 1 | Brownhills"; constituency cap excluding MSOAs in constituencies already holding a phase 1 or phase 2 place) · source ; MHCLG, "Local people take the lead in 40 more communities", 20 March 2026 · source ; Express & Star, "Brownhills to receive up to £20m government boost", 20 March 2026 · source
- Dudley College of Technology, "Dudley College of Technology named National Centre of Technical Excellence", 12 August 2025 · source ; WMCA, "West Midlands secures more funding to train the next generation of construction workers" · source
- MHCLG, "Historic council housebuilding comeback to help families into secure homes", 24 August 2026 — regional funding breakdown of estimated first-wave SAHP Strategic Partnership spend and homes by established mayoral strategic authority: Greater Manchester £529m / c.4,400 homes; West Midlands £409m / c.3,200 homes; North East £445m / c.3,400 homes; West Yorkshire £441m / c.4,000 homes; Liverpool City Region £380m / c.3,100 homes; South Yorkshire £249m / c.2,200 homes · source
Research notes
Verified from primary or council sources
- Housing Strategy 2020–2025 read first-hand via pdftotext: 908 net new homes a year (2017 standard-method evidence), 734 a year average delivery over the preceding five years, the 2018 Housing Deal's Walsall–Wolverhampton growth corridor ambition of c.8,500 homes by 2031, the 2003 stock transfer to whg and WATMOS with approximate current stock (whg 20,000, WATMOS 1,700, Longhurst/Beechdale 1,300, Accord c.4,200), and the council's five-year target of 50 construction apprenticeships and 100 pre-employment traineeships. [24,27]
- Pride in Place Impact Fund determinations read directly from the GOV.UK Annex A tables: Walsall at £750,000 in 2025/26 and £750,000 in 2026/27. [17,45]
- MHCLG's phase 2 place-selection note confirms Walsall's single phase-two neighbourhood as Blakenall South, matching the council's own naming. [42]
- The Local Plan consultation date was corrected during research: council coverage on 19 September 2026 states the Regulation 19 consultation launches Monday 21 September 2026 (six weeks, closing 2 November 2026); an earlier reported 14 September start appears to have been superseded. The government-set housing requirement of 21,026 homes, the draft plan's allocation of 14,943, the resulting shortfall of 6,083 and the submission deadline of 31 December 2026 were all read directly from the same 19 September 2026 report. [7,8]
- The Willenhall LUF2 award was confirmed as £20m, successful (announced January 2023), funding enabling works for the Moat Street/Villiers Street homes as part of a wider £210m Willenhall Garden City plan; a separate £19m Walsall South LUF2 theatre bid was unsuccessful. [43,44]
- Lockside (252 homes, former Caparo works) and the Metafin site (72 homes) were confirmed as two separate Anthem Lovell (whg/Lovell joint venture) consents; press coverage that sums them to 324 homes describes "the wider area," not one scheme. [22,23]
Open items
- Whether the Blakenall South independent chair has been appointed since applications closed on 18 August 2026 — still not verified. Searched the council's newsroom, invest.walsall.gov.uk, Valerie Vaz MP's site and Express & Star's Blakenall coverage; the most recent published item is the August 2026 application window.
- Brownhills board membership and chair — no council announcement found as at 19 September 2026. Searched the council newsroom, invest.walsall.gov.uk and Express & Star's Brownhills coverage; only the 20 March 2026 award announcement was found.
- Individual ward-level or project-level allocations for the £1.5m Impact Fund — the council states funding will be split across wards and three themes, but no ward list or project list is published.
- Whether the successor Walsall Borough Housing Strategy (consulted December 2025–January 2026) has been adopted.
- A Walsall-specific 2026/27 successor allocation for the wound-down UK Shared Prosperity Fund — not found; this money is understood to now sit inside WMCA's integrated settlement, as in other WMCA boroughs.
- The precise homes figure for the Willenhall/Moat Street "Locksmiths Quarter" scheme — sources give 100, 107 (outline permission) and 111; this briefing treats 107 as the outline-permission figure.
- The Darlaston governance dispute between the council-recognised board (chaired by Manjit Jhooty) and the rival community-organised board (chaired by Joyce Gibson) — unresolved in published sources.
Blocked or failed URLs
- https://go.walsall.gov.uk/planning-and-building-control/planning-policy/walsall-borough-local-plan — HTTP 404; the live page is the newsroom article cited at source 7.
- https://www.expressandstar.com/news/reform-to-press-for-flexbility-with-huge-housing-targets-in-walsall-9091476 — direct WebFetch returned HTTP 403; retrieved through the ScrapingBee helper instead (
scratchpad/sb/walsall/localplan_target.html). - https://www.expressandstar.com/news/business/2026/03/20/it-would-be-wrong-not-to-welcome-20million-government-boost-for-walsall-neighbourhood-council-leader-says/ — direct WebFetch returned HTTP 403; retrieved through ScrapingBee (
scratchpad/sb/walsall/blakenall1.html), though most of the facts used were confirmed instead from the council's own newsroom page (source 9). - https://www.walsallcollege.ac.uk/contact-us/ and the construction courses page — TLS certificate chain error on WebFetch ("unable to verify the first certificate"); the construction courses page was retrieved with curl instead.
Verification 19 Sep 2026
- Two wrong deadline statements corrected — this was the most consequential error in the brief. It said Darlaston, "as a phase-one place… must also submit its Pride in Place Plan to MHCLG by 26 February 2027", and repeated "the 26 February 2027 plan milestone for phase-one areas" in the milestones paragraph. The delivery guidance says the opposite: 26 February 2027 applies to the 40 phase 2 places named in March 2026 and phase 2 places in Wales, and phase 1 places have no plan deadline in the current timeline because they "have received their early capacity funding and are now in year 1 of delivery". Corrected in the dates table, the Pride in Place table, the milestones paragraph and the local funds table. [41]
- Walsall has three Pride in Place places, not two. Brownhills was missing entirely. Named on MHCLG's phase 2 expansion methodology note published 20 March 2026 ("Walsall | 1 | Brownhills"), £20m over ten years, plan due 26 February 2027. Added to the dates table, the Pride in Place section and the local funds table, and the section retitled "three places, three cohorts, one dispute". Also recorded why it sits in Aldridge-Brownhills: the expansion's constituency cap excluded MSOAs in constituencies that already held a phase 1 or phase 2 place. [57]
- Flagged that council and press coverage of the Brownhills award quoted a November 2026 plan deadline, which is the earlier phase 2 cohort's date, not this one. A reader working to November would be working to the wrong date by three months.
- Darlaston's phase 1 status upgraded from inference to primary: confirmed on MHCLG's phase 1 place-selection methodology note ("West Midlands | Walsall | Darlaston"). Blakenall South re-confirmed on the phase 2 note, with "single phase-two neighbourhood" reworded to "single original phase 2 neighbourhood" now that Brownhills exists. [42,56]
- Citation error corrected. The Construction Technical Excellence College paragraph cited "[13,14]" — Walsall's [13] is the Darlaston Plan board page and [14] an Express & Star Darlaston article, neither of which supports a CTEC claim. Replaced with a new source 58 (Dudley College's own designation release and WMCA's announcement), and the CTEC detail expanded with the funding split, delivery sites and employer contact.
- SAHP first-wave wording corrected in the milestones table: the release states no grant or homes total; its partner table sums to £9,584.1m and 73,617 homes, each partner capped at £350.0m. Also re-checked the claim that whg and Accord are not among the 33 partners — correct, neither appears in the partner table. [2]
- SAHP first-wave regional estimate added. MHCLG's release of 24 August 2026, "Historic council housebuilding comeback to help families into secure homes," publishes a regional funding breakdown giving the West Midlands an estimated £409m and around 3,200 homes for first-wave Strategic Partnership spend — MHCLG's own regional estimate, not a Walsall award. [59]
- Impact Fund re-checked against both Annex A determinations: Walsall £750,000 in each of 2025/26 and 2026/27. Correct as written. [17,45]
- Pride in Place funding profile added from the delivery guidance. Procurement re-checked: Walsall's own In-tend instance, 01922 658471. Unchanged.
- Willenhall / Moat Street homes number re-examined and left at 107 (outline permission, 16 July 2024, 54 apartments and 53 houses), with "around 100" and "111" treated as rounded press figures. No newer council decision record was found that supersedes the outline figure; the brief's existing treatment is correct and stays.
- Still open after search: the Blakenall South and Brownhills chairs; whether the successor Walsall Borough Housing Strategy to 2040 (consulted 15 December 2025 – 26 January 2026) has been adopted — searched the council newsroom and housing pages, only the consultation announcement is published; a Walsall-specific 2026/27 UKSPF successor allocation; the Darlaston governance dispute.
- Citation numbers: all [n] resolve; three new entries added (56–58) without renumbering, and no collisions.
General information only, not legal, financial or professional advice. Confirm eligibility and terms with the relevant body.